Major Works Overview
Construction of Bridge Over River Indus for Diamer Bhasha Dam Project

It is basically an access bridge over river Indus for Diamer Bhasha Dam. Then length of bridge is 312 meter. It is a balanced cantilever box girder bridge with central span of 156 meter and two side spans of 78 meter each. It is a challenging job because for side of bridge is inaccessible and then other challenge is its left pier. The pile cap of this pier is underwater. The soffit of pile cap is at the level of 941.35 whereas water level in month of April is 953 which will start raising in May and reach at 968+00 or even more in case of flood.
Cost of Project Rs 1304 Million
Client Frontier Works Organization
Length of Bridge 312 Meter
Start Date Feb 21
Completion Date May 24
Type of Work Cantilever Box Girder Bridge
- ESTABLISHMENT OF 200 BEDS GENERAL HOSPITAL (I/C) MCH & EYE HOSPITAL RAWALAKOT DISTRICT POONCH AJ&K PHASE-II.
This is an extension of the existing Hospital Facilities which comprises remaining work of 200 Beds MCH & Eye Hospital, main building, external development, Doctor Apartments, Paramedical Staff Hostel, Nursing Hostel, Doctor Hostel and External Water Supply arrangement. The project is situated in the city of Rawalakot AJK.
Cost of Project Rs 696 Million
Client PWD Building/PHE (North) Muzaffarabad
Start Date Jan 21
Completion Date Dec 24
Type of Work Building Works
No. of Buildings 08
Total Covered Area 150000 Sft
- CONSTRUCTION OF MAKRI INTAKE WEIR AND INSTALLATION OF FLOW METERING SYSTEM.

Due to Neelum Jhelum Hydropower Project water in Neelum River is reduced after Nosehri due to which a shortage in water supply to Muzaffarabad is expected during low water season. This project is mainly construction of Weir on river Jhelum at Makri to raise water level at this point and to make intake structure to keep the water supply intact;
Cost of Project Rs 862.773 Million
Client PHE Division, Muzaffarabad
Start Date June 2020
Completion Date May 2022
- UPGRADATION AND RECONDITIONING OF SHARDA – KEL ROAD
This road is between Sharda and Kel (18.1Km) in a Neelum Valley, AJK. This is an important road strategically as well for tourism. It is basically a hill road with river on one side and hills on other side. It is a remote area which make construction as well road is to keep operational during construction;
Cost of Project Rs 553.379 Million
Client PWD Highway Division, Neelum
Start Date June 2020
Completion Date May 2023
CONSTRUCTION OF MIR WAIZ MUHAMMAD FAROOQ SHAHEED MEDICAL COLLEGE, AJK

This building project comprised of 11 buildings with a total covered area of 260000 sft. Being a part of Abbasi Institute of Medical Sciences (AIMS) this building will serve as Medical College;
Cost of Project Rs 1903.558 Million
Client PWD, AJK
Start Date December 2016
Completion Date June 2024
No. of Buildings 11
Covered Area 260000 Sft
MAJOR PROJECTS COMPLETED
- REHABILITATION OF BRIDGES
Along with construction of bridges the company has capacity and capability of rehabilitation of bridges as well. Following rehabilitation has been executed under the profile of Engr. M. Fayyaz Zaeem and Engr. Mansoor Iqbal.
Rehabilitation works consist of Micropiling, anchoring for creating bond between eccentric well caps and brick masonry, Repair of eroded and displaced brick masonry, External pre-stressing to enhance the overall integrity of the structure, Replacement of bearing pads to reduce the impact on structure, Repair of cracks by using epoxy grouts, Repair of expansion joints to improve the riding quality, Re-grouting of existing cables, Application of waterproofing compound, Improvement of Asphaltic wearing surface and drainage facilities.
- Rehabilitation of Bridge over River Indus Ghazi Ghat.
- Rehabilitation of Bridge over River Sutlej, Bahawalpur
- Rehabilitation of Kunhar Bridge, Balakot AJK.
- Rehabilitation of Ayub Bridge, Havelian.
- Rehabilitation of Dina Bridge, Main G.T Road
- Rehabilitation of Misakaswal Bridge.
- Rehabilitation of Head Punjnad Bridge.
- Rehabilitation of Kharrapa Bridge Over Indus Highway
- Rehabilitation of Ayub Bridge Havelian at Km 56+050 KKH, (N-35)
BOX GIRDER BRIDGES
- CONSTRUCTION OF RCC BRIDGE KOTLI TATTAPANI ROAD

This is a balance cantilever box girder bridge on river Poonch at Tattapani Road, Kotli. Balanced cantilever construction is a phased construction of a bridge superstructure. The construction starts from the piers cantilevering out to both sides in such a way that each phase is tied to the previous ones by post-tensioning tendons, incorporated into the permanent structure, so that each phase serves as a construction base for the following one. The bridge was of strategic nature as it connected Kotli with the border area, Tatta Pani. Keeping in view the environmental protection of the aqua culture, the design of the bridge was specially designed as the location of the bridge is situated in the National Park and also consists critical habitat.
Our company is first Pakistani Company who has already completed two cantilever box girder bridges on rivers and has completed its 3rd bridge of the same type.
Cost of Project Rs 449.68 Millions
Client Communication & Works Deptt, AJK
Financed By Asian Development Bank
Start Date January 2018
Completion Date April 2019
Length of Bridge 160.42 Meter
Central Span 136.15 Meter
Right Span 15.125 meter
Left Span 9.15 Meter
Width of Bridge 10.70 Meter
Width of Carriage way 8.50 Meter
Width of Foot Path 1.20 Meter
Type of Bridge Balance Cantilever Box girder
- CONSTRUCTION OF LANGARPURA BRIDGE OVER RIVER JHELUM, AJK

Balanced cantilever segmental construction for concrete box-girder bridges has long been recognized as one of the most efficient methods of building bridges without the need for falsework. This method has great advantages over other forms of construction in urban areas where temporary shoring would disrupt traffic and services below, in deep gorges, and over waterways where falsework would not only be expensive but also a hazard. Construction commences from the permanent piers and proceeds in a “balanced” manner to midspan. A final closure joint connects cantilevers from adjacent piers. The structure is hence self-supporting at all stages. Nominal outof-balance forces due to loads on the cantilever can be resisted by several methods where any temporary equipment is reusable from pier to pier.
Bridge over River Jhelum at Langarpura, Muzaffarabad AJK is an example of unbalanced cantilever box girder bridge, which is designed to provide access to Langarpura Town Ship Scheme primarily for earthquake affecties of 2005. The bridge was successfully completed in September 2016.
Cost of Project Rs 419 Million
Client Earthquake Reconstruction & Rehabilitation Authority
Main Contractor M/s China Xinjiang Beixin Construction Group
Start Date May 2013
Completion Date November 2016
Length of the Bridge 122 Meter
Width of Carriage way 8.5 Meter
Width of Pedestrian Passage 1.2 Meter
Type of Construction Pre-stressed Box Girder Segmental Construction using Traveler Form Work
- CONSTRUCTION BRIDGE OVER RIVER NEELUM AT JALALABAD, MUZAFFARABAD

The company is one among few in Pakistan who have constructed balanced cantilever box girder bridges on rivers. This is the first Box Girder Balanced Cantilever Bridge executed by us. The construction of the box over the piers is performed by overhead traveler gantry. The box segments are cast in place with hollow shape of box. This bridge is located in the center of city and was completed in September 2014, with salient features as below;
Cost of Project Rs 365 Million
Client Earthquake Reconstruction & Rehabilitation Authority
Main Contractor M/s China Xinjiang Beixin Construction Group
Start Date November 2012
Completion Date September 2014
Length of Bridge 123.970 Meter
Central Span 67.50 Meter
End Spans 30 meter & 26.415 meter
Width of Bridge 10.70 Meter
Width of Carriage way 7.30 Meter
Width of Foot Path 1.20 Meter
Type of Bridge Balance Cantilever Box girder
Method of Construction: Pre-stressed segmental construction using overhead gantries
Type of Foundation Shallow Foundation
- CONSTRUCTION OF 14.4 MW JHING HYDROPOWER PROJECT

Jhing is situated approx. 30 km from Muzaffaraabd City at Neelum Road. Hydropower projects use a well-established method of generating electricity that uses moving water (kinetic energy) to produce electricity. This production unit has been linked with National Grid. The project consists of construction of Forebay and wasteway, Penstock supports and Anchor Blocks, Powerhouse, Tail Race, Staff Quarters and Access Road.
Cost of Project Rs 521.8 Million
Client Power Development Organization, AJK
Start Date June 2016
Completion Date May 2021
Type of Work Mechanical and Civil
- RECONSTRUCTION OF AZAD PATTAN RAWALAKOT ROAD

This is a major artery of AJK, which links Azad Pattan and Rawalakot. Length of road under this project is 33 Km, being constructed under Flood Emergency Reconstruction & Resilience Project (FERRP) funded by Asian Development Bank (ADB);
Cost of Project Rs 1569.89 Million
Client PIU, FERRP C&W, AJK
Start Date January 2017
Completion Date March 2019
Length of Road 33 Km
Type of Road Asphaltic Road
- RECONSTRUCTION OF RAWALAKOT HAJIRA ROAD

This is a major defence road of LOC in AJK having length of 20 Km, being constructed under Flood Emergency Reconstruction & Resilience Project (FERRP) funded by Asian Development Bank (ADB);
Cost of Project Rs 647.582 Million
Client PIU, FERRP C&W, AJK
Start Date May 2017
Completion Date October 2018
Length of Road 20 Km
Type of Road Asphaltic Road
- CONSTRUCTION OF PRIME MINISTER HOUSE MUZAFFARABAD AJK

Prime Minister House was a building complex comprising of different buildings both residential and offices for the Prime Minister of AJK. The project was completed in 2017. The salient features of the project are as under;
Cost of Project Rs 457 Million
Client China International Water & Electric Corp (CWE)
Start Date June 2013
Completion Date April 2016
No. of Buildings 11 Nos
Area of the Project 190,400 sft
Type of Construction RCC Framed Structure
- CONSTRUCTION OF WORKING WOMEN HOSTEL, AT SALCC H-8 ISLAMABAD

The building is being constructed to facilitate accommodation working women. Building consist of G+2 floors, with total covered area around 23000 Sft;
Cost of Project Rs 47.130 Million
Client Sindh Graduate Association (SGA)
Start Date January 2018
Completion Date June 2019
No. of Floors G+2
Covered Area 23000 sft
- CONSTRUCTION OF WATER TREATMENT PLANT AT MAKRI MUZAFFARABAD AJK

Water Treatment plant at Makri Muzaffarabad was a part of water supply enhancement project to the city of Muzaffarabad. It consisted the construction of Filter beds, Machine Hall, Clarifiers, connecting channels etc. The said project was completed in 2017. The salient features of the project are as under;
Cost of Project Rs 226 Million
Client China International Water & Electric Corp (CWE)
Start Date April 2014
Completion Date April 2016
No. of Clarifiers 02 Nos
Filter & Machine Hall Building 01 No
Connecting Channel 01 No
Pre Settling Tank & Flash Mixer 01 No Each
- CONSTRUCTION OF ACCESS BRIDGE OVER RIVER JHELUM FOR PATRIND HYDROPOWER PROJECT, AJK

Company has the honour to construct first multi-span continuous ‘I’ shape girder bridge in Pakistan on River Jhelum. Each ‘I’ shape girder is 175.35 m long and is stressed partially before and partially after launching.
Cost of Project Rs 258 Million
Client Sambu Pakistan (Pvt) Ltd
Start Date October 2010
Completion Date July 2012
Length of Bridge 175.35 Meters
Central Span 65 Meters
End Spans 50 meters
Width of Bridge 10.70 Meters
Width of Carriage way 7.30 Meters
Width of Foot Path 1.20 Meters
Type of Bridge Multi-span continuous ‘I’ shape girder
- CONSTRUCTION OF THOTA BRIDGE OVER RIVER JHELUM, AJK

This bridge is 2nd in Pakistan of its type multi-span continuous ‘I’ shape Girder Bridge completed in November 2016, with salient features as below;
Cost of Project Rs 309 Million
Client M/s China Xinjiang Beixin Construction Group
Start Date January 2014
Completion Date November 2016
Length of the Bridge 110.78 Meter
Central Span 58 Meter
Side Spans 2 x 26.39 Meter
Width of Carriage way 8.5 Meter
Width of Pedestrian Passage 1.2 Meter
Type of Construction Pre-stressed Pre cast multi-span ‘I’ shape girder bridge
- CONSTRUCTION OF PESHAWAR MORE INTERCHANGE-MBS-PACKAGE-II ISLAMABAD

The company has the honor to participate in the prestigious project of Rawalpindi Islamabad Metro Bus Project and working on the biggest of all eight sections i.e. Islamabad Package-II. The company has undertaken the following portions of Metro Bus corridor;
- Metro Bus Corridor including Bus Station
- Six small bridges
- Half a kilometer long huge 3 cells box culvert,
- More than a kilometer long 72” Ø RCC pipe line in two rows
- 1 Km long Pedestrian Underpasses
- Interchange comprised of eight flyovers having multi-span continuous pre-stressed box girders having total length of 4.1 Km.
Cost of Project Rs 4,120 Million
Client National Logistics Cell / RDA
Start Date May 2014
Completion Date March 2016
- CONSTRUCTION OF VEHICULAR UNDERPASS, NEAR DISTT COURT RAWALPINDI

The company has specialized in construction of pre-cast underpasses on fast track basis and has successfully completed around a dozen underpasses on various locations on N-5 having sizes from 3m x 3m upto 10m x 5.1m (internal size). Company has another distinction of using tunnel formwork in construction of Box Culverts and has successfully completed a 88m long 3 cell box culvert of 2 x 9.3m x 5.2m (for vehicular traffic) + 1 x 5.5m x 5.2m (for railway train) at junction of Adyala road and N-5 near district courts, Rawalpindi.
Cost of Project Rs 182.98 Million
Client National Logistics Cell
Start Date December 2008
Completion Date March 2011
- SMALL HYDROPOWER PROJECTS
- Lining of diversion Tunnel No. 1 & 2 at 102MW Gulpur Hydro Power Project
- Sharda Hydropower Project (Restoration of Flood Resilience Protection of Structure)
- Penstock Pipe for 1.79MW Dhanna HPP, District Kotli 2 x 800 KW Hajira Hydropower Project
- Penstock Pipe for 2×1000 KW Kapa Banamula HPP, District Hattian Bala.
- Construction of intake Sluiceway at 4.8MW Battar Hydropower Project Distt Havelian.
- Providing, Laying, Welding and concreting of Wasteway Pipe at 4.8MW Battar Hydropower Project Distt Havelian.
- Remaining Penstock and Spillway Works of 2x500KW Bhedi Doba Hydropower Project, Distt Haveli AJK
- Secant Pile Wall around Power House at Patrind Hydropower Project, Muzaffarabad, AJK.